Evacuation simulation of a production hall
In order to ensure occupational safety in a factory hall and to check the necessity of rebuilding measures, accu:rate was commissioned with a pedestrian flow simulation.

Description
Task: Evacuation simulation
Result:Proof of safe evacuation
Result:Proof of safe evacuation
Background
Business continuity is a top priority, especially in the automotive industry. An important aspect here is occupational safety and preventive fire protection. Innovative companies in particular rely on new technologies such as crowd simulation. accu:rate was therefore commissioned by a renowned fire protection agency to examine the evacuation concept of a major German corporation.
Objective of the simulation
The evacuation simulation was used to check if reconstruction measures are necessary in a production hall to ensure the safety of the employees or if the current measures are sufficient.
Our approach
- Evacuation of a factory hall when fully occupied
- Examination of escape routes and evaluation of possible conversion measures
Results
The results of the simulation show that there is no need for any reconstruction measures. Despite the longer escape route in case of an evacuation, all staff can leave the building in time.
The simulation was added to the fire protection concept as compensation, which meant that the complex and expensive construction measures could be saved.
Image sources:
Photo by Jean-Luc Valentin via Wikipedia (CC-BY-SA-4.0)
https://upload.wikimedia.org/wikipedia/commons/d/d3/Blick_in_die_Produktion.jpg
Do you have a similar project or would you like more information?
We look forward to hearing from you!